Week 85

The contractors are back this week to sort out immediate Stuff. These include things like painting the garage floor and filling large gaps in blockwork in the walls out there, fixing the rainwater diverters, sorting my neighbour’s drive, and changing the loft boards. What’s been lacking on our side is any kind of oversight or ensuring that the work is carried out to the expected standard. So, …drumroll, please… we welcome Phillip to the role of Contract Administrator III. He’s the new Alyson/Ben, and so far he’s a total rock star. He’s come in, assessed the build, found 65 items to put on the rectification list, and written a comprehensive report, with photographic evidence!, to circulate. Why oh why didn’t we hire him earlier?? He’s a cyclist as well which makes his appointment even more jammy.

While Tim has been dicking me around on timing by deliberately not letting me know what the plan is or what he’ll be doing during his Week of Fixing Stuff, I’ve been biding some time for Phillip to get up to speed and take the reins. Brave man is Phillip, jumping on board this moving train. Meanwhile: patience, patience, patience. I won’t be rushing to contact Tim through his lawyers as per recent arrangements to get stuff like rainwater pipework and the insulation complete, I’ll wait it out, try to chillax about the When, and leave it all to Phillip.

Although he’s employed by us, it will be Phillip’s job to impartially enforce the contract as CA. That means that he makes Tim do the stuff he said he’d do, and he makes us pay the stuff we said we’d pay. Our spanner in these works is that thanks to previous management’s weird ideas about signing off everything willy-nilly without checking properly, we’ve paid…

e v e r y t h i n g

…in full. Usually, in a normal world, that would put us in an unenviable position leaving us exposed for overpaying for an incomplete job. But in the Weird World of Building, this is entirely normal; lots of contractors won’t even talk to you unless you’ve paid them first, never mind actually show up and do anything. Three years in and there is so so so much I still don’t understand about all this.

So, returning to the day-to-day….. Mike’s been back with his paint brush to paint the garage floor. You may remember that this was the solution given when it was discovered that a 1 cubic metre hole had to be butchered out of the pristine garage slab (and rebar) to re-route the water pipe that somehow was seen fit to be installed too close to ground level. The reinstatement of the concrete floor left a great big square of different concrete which isn’t cool. The rectifying painting never happened, so they’ve come back to do it now. Over last weekend just gone, in preparation, we, and the now-very-grumpy children, had set up the scouts’ mess tent (thank you 1st Oxshott) in the garden to temporarily house all our Stuff.

house 2017.11.23 - 1 (3).jpg
temporary garage
house 2017.11.23 - 2 (1).jpg
leaning tower of tent

Dave recommended Watco products as the fix, and Mike got set to work on the first day cleaning out the dust, cutting back the plastic around the perimeter and using their Etch and Clean product to provide a good base. That took overnight to dry, so painting started the following day. First coat down and Mike was off to his next job while it dried before the second coat scheduled for our third day of fun and games. Luck would have it that we’d had a storm blowing through the last few days, and you’ll recall that we live right near the heath. This combination is a bit toxic for painting garage floors as loads of beech and oak leaves swirled around in the breeze and blew directly through the door that Mike had left open and onto the newly laid paint.

house 2017.11.23 - 1.jpg
brilliant

I couldn’t get in there to remove them because the paint was wet. So I left it. Not my usual vibe as 9 times out of 10 I’m a get-stuck-in-and-sort-it-out kind of girl. Although this was frustrating to see, in actual fact I think the leaves didn’t stick too badly, and the second coat hopefully would have erased whatever slight marks the pesky leaves would have left anyway.  I haven’t been in to check because it takes a few days to get seriously un-wet. But,… reminds me of Michael Roux. It will be nice we can repeat our Grand Move of Stuff back into the garage in reverse and return the mess tent to the scouts.

The environmental guys visited this week to inspect the mould in the loft. They tested all the boards with their whizzy little water meter and found the really mouldy ones to be around 30%. They should be around 15%. To our horror, they suggested that the problem wasn’t left-over damp from the flood, but instead, that the flat roof between Gillian’s room and the main structural oak frame is leaking or allowing condensation to build. They think that either it’s a seal that’s properly gone, or that a thermal barrier is missing and making water condense on the boards, causing them to grow their fuzzy mouldy surface. And the growth on the floor is due to spores flying around and settling onto it. Ew.

house 2017.11.23 - 1 (2).jpg
one of the mouldy boards
house 2017.11.23 - 1 (1).jpg
a row of mouldy boards

This means that the whole problem shifts its Sauron-like focus from the insurers re the leak, to Tim re general building and warranty. But he doesn’t know this yet. The environmental report is due out soon and will go first to the loss adjusters and maybe then on to the insurers. I’ve just got to make sure that Tim gets a copy of it so that we can start the ball rolling and get it fixed. I spent most of my day yesterday wandering around in a disbelieving daze wondering how things could get any worse than they already were.

In a fit of wisdom and unusual allocation of resources, Tim sent Josh the young chippy, his finance guy and Dulux to tear up the horrible bit of destroyed rear drive and replace with a 6″ deep concrete float. Nothing like having experts do the job they’re trained to do. All nice guys, but I’d expected Lee and the groundwork guys to do, er, groundworks. James reckoned there were a couple of metres square that needed replacing, but he’d forgotten about the temporary tarmac and barrowfuls of hardcore shoring up the drive they’d put down during last year’s rains. He marked his assumption in yellow.

house 2017.11.23 - 1 (7).jpg
that’s not quite all the horrible-ness, James

All in all, there’s about 12 square metres to replace from corner to corner, and to his credit, they re-marked the larger area before they set to work. And the leftover bit from the demolition needs a clean line cut into concrete as well. Luckily, Mark and his landscaping team put us off for another week, so they won’t have to face setting their fence up and having dead slabs in the way.

house 2017.11.23 - 1 (5).jpg
digging out the broken bits
house 2017.11.23 - 4.jpg
ear defenders are for wimps “I’m deaf anyway!” shouts Dulux

Concrete was poured by the afternoon, and it was looking great until they said that they’d be back next week to remove the kango-ed out spoil. Whoa! Brakes on! No, they’re supposed to FINISH THE JOB and take it all away TODAY. Full truck, I’m afraid, madam. What about my landscapers who are coming next week to put up my fence right through the middle of your pile of shite? Sorry, we only do what we’re told, and we’re clearing another site tomorrow, so that leaves us next week.

Sigh.

house 2017.11.23 - 2 (2).jpg
concrete
house 2017.11.23 - 1 (6).jpg
shite

Oh yeah, and it rained this week. So that means despite Ricky’s magic touch with a silicone gun, the outdoor lights tripped.

Again.

Week 74

The final bills are rolling in, the site is gradually becoming clearer and clearer of rubbish each day, and we can just about make out the horizon. It’s still a long way off, but we passed another milestone this week and I actually got in touch with Andy again about sorting out dates for the final moving-in. It will be our fourth move, not counting the move into and out of storage

The drive groundsmen left site on Friday having cut blocks into slivers all week to fill gaps and fiddled with man-hole covers to set the patterns without interruption. They look great, but the neighbours weren’t enormously impressed with the noise and dust of the table saw.

house 2017.09.10 - 7.jpg
main sewer manhole cover
house 2017.09.10 - 13.jpg
cuts for groundlights
house 2017.09.10 - 6.jpg
rainwater surround
house 2017.09.10 - 12.jpg
granite setts bordering garage door
house 2017.09.10 - 2.jpg
porch mid-flow
house 2017.09.10 - 14.jpg
pre-pointed porch
house 2017.09.10 - 8.jpg
freshly pointed porch
house 2017.09.10 - 9.jpg
back fence pre-slabs

The car-charging post is A Big Deal, mainly because it’s a bit esoteric and involves Neil to make the thing, the chippies, the grounds guys and the electricians none of whom had done this sort of thing before. We wanted to site it at the corner of the parking bay by the fence, so, in theory, if we ever had two electric cars, the chargers could share the single post. But although Pat had dug a lovely trench for it all along the line of setts, the conduit wasn’t long enough, so we ended up choosing a spot right in the centre for it.

house 2017.09.10 - 10.jpg
where to put the post?
house 2017.09.10 - 3.jpg
here
house 2017.09.10 - 4.jpg
back of the post

The three-phase conduit is running inside a large ribbed duct which houses the wires wrapped in armoured shielding. It needs two bends to get to the charing unit: one from underground to start running up the groove in the back of the post, and another to run through a hole from the back of the post to the charging unit in the front. The armoured sheath causes bends to happen at a really wide diameter which makes it sit proud of the groove. Not cool. So Steve had a brainwave to terminate the sheath inside a recessed box and run the wires through the post freely where’d they be safe anyway. The photo shows the conduit without the box, and you can see the box being chipped into the post in the time lapse.

Another piece of electrical good news was overcoming wiring up the lamppost.  Steve was sure that the thing was set in concrete and that we’d have to dig up the whole thing to get a wire through. Luckily, a little scrabbling on hands and knees revealed a hole at the base of the lamp undergorund to run the cable through and up to the top. The sparkies quickly ran some rods up the post to check it was clear, and they wired it all up in half an hour.

house 2017.09.10 - 5.jpg
coast is clear for wires

And just to ensure that a good test was given to the ditch before the guys finished, it hammered down.

house 2017.09.10 - 11.jpg
a river runs through it

Deeks is getting a clear run at snagging this week, as I’m getting preoccupied with fireplace, steel cladding and landscape gardening. Alyson recommended I stay out of their hair for a bit in any case. The cleaners come on Wednesday as do the electricians and the Rako commissioning guy. Thursday must be for tidying up and doing outside work. Friday is Practical Completion which is amazing. Next Monday I walk round with Alyson, and next Tuesday is a day for settling final accounts with Tim.

I feel quite emotional about finishing. Gregory will be going off to uni before we move in, and the moving in itself, the budget and all the work it’s going to take to get the house sorted is daunting. We won’t have curtains despite Rachel’s excellent help in getting us there. No money.  No wardrobe in our bedroom either. No money. No hanging lights, no furniture, no garage storage. It’s a little depressing because we had budgeted for all this at the outset. It wasn’t an enormous budget–nothing grand or gold-plated–but enough to sort these last few bits out. Instead, we’ve spent it on rent and management for 10 excruciating months. I know that I’ve bought a T-shirt and a book of tickets to my very own pity party, and that doesn’t feel right either. I think it’s more of setting myself a goal that isn’t turning out right. It’s the OCD part of me that is upset, not the Surrey-housewife part (that part is pretty small anyway). I’m not very good at changing gears. The most emotional part is that I’ve let the family down. But they’ve been awesome during this whole thing, and afterwards, I’ll be stronger and they’ll just keep on being awesome. Clinton is already planning the next build. (omg)

The loss adjuster is proving painstaking about invoices and their wording too. I know it’s his job to be responsible for extracting cash out of the insurers, but he’s rejected my invoices from architects and contract management because they don’t refer directly to Water Damage. I would have thought that everything happening after the original PC of 20 June was a result of Water Damage otherwise we wouldn’t have had to do it. But no, I’ve got to get the extra info onto the paperwork, and it will be difficult to get it from Ben whom we haven’t heard from in a fortnight.

So, we’re almost there. Fingers crossed for no big issues at the end. Again.

 

 

Week 73

As we lurch into another week of very little happening on remedial works compared with masses accomplished on the driveway, I’ll start this post with a bit of a change in tone. The blog has gone from Public to Private to keep the project’s chronological recordings from being used by lawyers, and since you’ve suffered through the rigamarole of answering invitations and creating log-ins and passwords to get access here, let me reward you by gently leading you towards the edge of the rabbit hole to peer down at what’s really been going down behind my previously sugar-coated versions of my eleventy bloody billion previous posts.

The post-flood remedial works are supposed to be complete by 16 September. This would be funny if we hadn’t been here before; now it’s just business as usual. It includes both a builders clean and a sparkle clean as well as the handover of The O&M Manual. Just that alone should take about two weeks! O is for Operations, but I’m a little hazy on M if it’s not Manual, as it would then be an Operations and Manual Manual. ?? Tim’s plan such as it is, has the electricians in Tuesdau (HA!–still hadn’t had confirmation of their arrival by last Friday), decorating and groundworks complete, joinery assembled and snagging finished by Friday, leaving room for the cleaners to be in early next week. Clearly, pigs are aloft in Oxshott, and there’s nothing we can do but watch this oncoming train wreck. For the third time.

The biggest problem is that there’s no stipulation of timing with the insurance works–the loss adjuster is only interested in cost. Our rent and associated Liquidated Ascertained Damages are considered uninsured losses and aren’t covered in the remedial works, but a small teensy portion of them is covered in the JCT, the main contract of the build. And the kicker with that is that when we took advice from Ben at the beginning, we set the LADs to be £500 a week which just about only covered our rent and not a lot else. Clearly this is no where near enough and doesn’t cover things like numerous removals, setting up services at a rental property, storage costs, postal redirection, estate agents fees or wear and tear on one’s soul. We’ve got a discussion to have with Ben, but….

Anyway, as there’s never been a dull moment on this project, er, apart from the bricklayers’ one-week strike…. or maybe the plasterers’ scheduled three week/actual six week stint (unbelievable),…. the biggest hiccup this week is that Ben has left. He has suffered a bit of a breakdown and if he told me that half the problem was bullying by our contractor, I wouldn’t be surprised. His girlfriend wrote to us on Friday effectively resigning him, and his out-of-office email says the office is closed until Autumn 2017. It’s a huge blow to him personally, and it’s horrible for him I’m sure. But professionally, it leaves us right up the creek without our paddles.

The contract requires a Contract Administrator, and because Tim is Tim, and he is entitled to do so in the contract, he won’t do any work at all without one. So we’ve hired Alyson (welcome, Alyson) from Aspire, the driveway crowd (who’s doing an awesome job), to pick up the pieces and see us across the finish line. It’s the logical solution as their values as a company are exemplary, the work they’re doing on the drive will actually be done early (Shocking.  I know.), and they know the landscape (sorry) of developing houses in the area. Tim’s already objected that us hiring her is a conflict of interest, and to object to her appointment is another one of his entitlements under contract, but I’m not sure if it’s in his interest or if an adjudicator would agree with him, because we all simply want this wrapped up. Perhaps Tim will relax into this new appointment, and I hope he does for everyone’s sake. Alyson is meeting with Tim this week, and hopefully they can get started without drama.

The JCT says that the contractor has to make “regular and diligent progress.” Diligence is a little suspect because as you can see on the time-lapse, although Mike is armed with paints and brushes, he’s spent an awful lot of that time talking to the Aspire guys outside. Everyone’s really waiting for the flooring guys to finish laying the wood upstairs before any real work can start. They’d done a lot of the joinery work before the flooring went down: some of the doors needed replacing and lots of warped architrave was reinstated. You’d think that after Tuesday when the flooring was finished, that they’d be onsite in force. But, sadly, no. Still no site manager, still no programme. Tiles and skirting hadn’t been ordered, groundworkers were nowhere to be seen, and, surprise, no sparkies had attended for weeks. I would like to be pleasantly surprised to have these things in place and all mapped out. But I’m still waiting even now.  It’s a big ask for Alyson to wade in at this eleventh hour, she seems up for the challenge, and we’re putting a lot of faith in her.

Dave completed the snagging list over the weekend ready to give to Tim today. Everyone loves a list because you can simply tick things off which gives an enormous sense of progress. The challenge is to put some perspective on the individual items. Some, like reinstating the driveways for our long-suffering neighbour round the back are huge. Others, like picking up a single bolt off a windowsill, are insignificant. It’s great that the list is done and distributed, but I can’t honestly see the more than 200 items being scheduled and done by next Friday.  Do you?

Take a look at the electrical cupboard for instance. It needed to be completely reinstalled because it sat right in the path of the waterfall back in June. The sequence of works to fix it involves the electricians, our appointed security guy doing the alarm, the plumbers doing the heating manifold, the joiners and the decorators to each do their thing. You’d obviously think, “oooo this requires careful sequencing of trades.” What we’ve ended up with is everyone doing a little bit when they can, nothing getting completely done, and a shocking puzzle pieces arrangement of build-out joinery to cover it all: wires sticking out, bare blockwork behind pipes, unintelligible arrangements of wires….. What we want, and what’s on the snagging list to be done, is a quality finished cupboard. This isn’t it.

house 2017.09.04 - 5
don’t get me started

Enough griping. I haven’t put any time-lapses on the blog for a while so I’ve put a bunch showing progress made on the drive at the bottom of this post. In the meantime, here’s a lovely tiny video of some hawk action one day when visiting site (Allison, can you tell what these creatures are?) and a few photos front and back.

house 2017.09.04 - 1.jpg
it will get less stripe-y when they tamp it down and add sand to the joints
house 2017.09.04 - 2.jpg
digger’s last week coming up
house 2017.09.04 - 4.jpg
rear garden still to be sieved

Next week we’re supposed to see tilers, joiners, grounds-guys, electricians and decorators. And the kitchen company because someone has dinged one of the doors and it needs replacing. I’m sure much of this will happen, but the problem with having a load of trades in all at once is that it gets crowded and work actually slows down. We’ll check the snagging list against how much progress was made on Friday.

In the meantime, the drive will be finished a few days early. Go figure.