Week 42

house201701.24 - 1.jpg

Roof tiles arrived this week. Spencer and his team used the tile-escalator, or Bumpa, to haul 10,000 tiles up to the roof. That is TEN THOUSAND. A totally bonkers number.

2017.01.24-2.jpg

We’re very happy with the colour. Although we didn’t use a huge mix of colours in the end, having gone for mostly Heritage, Michelmersch, they still look really mottled when they’re on, and that’s the look we were going for. The colour changes a lot in the light, and it will darken over time.

2017.01.24-5.jpg

2017.01.24-6.jpg
frozen tiles
2017.01.24-7.jpg
they frost up on the north side of the house

2017.01.24-8.jpg

2017.01.24-3.jpg
Josh with saw, not enjoying puzzle-piecing the insulation

Josh, Terry and James are cutting up bits of insulation to fit in the rafters. Not a super fun task, but they’re getting on with it bravely. In fact, it’s their absolutely least favourite thing to do in the whole build because they’ve got to get all dolled up in their anti-dust gear complete with masks and as much full-length coverage as possible to avoid fibres sneaking into clothes and itching all to hell. And we’ve got tons of the stuff. Some of the long sections will have rolls of insulation, which gives a small respite, and these will be installed after the plasterboard ceilings are put up so they don’t drop down through the gaps.

Once the solid insulation is installed, they tack up large bits of fancy tin-foil to make it even cosier.

house201701.24 - 2.jpg
tin foil ceiling in back bedroom….
house2017.01.28 - 1.jpg
… now covered in plasterboard later in the week

2017.01.28-8.jpg

A small issue percolated to the surface with lining up the glazing bars on the west and north faces in the front landing first floor bay. We’re still discussing how to deal with it. But the rest of the windows are going in nicely.

2017.01.24-4.jpg

We’ve got another issue with the glazing bars in the back of the house too, and this is more of a design thing. They don’t line up either. But is it a problem at all? Architects would probably recoil in horror and shout “Of course!”, but this is a one off house, right? It’s the crack in the pot in the great grand scheme of things. Making them line up would require masses of redesign from the bricks to the subframes and on to replacing windows and frames. Tim reckons that once it’s decorated and furnished we won’t notice it so much. He’s probably right. My plan is to plant the heck out of the garden so you see through the windows (obvious but important here) into awesomeness.

house2017.01.28 - 5.jpg
is it a problem?

The kitemarks were such a bugbear at the beginning of the build with the warranty company insisting that they were visible ON EVERY PANE. There are 98 panes. That was clearly not the option we wanted, and after many flurries of emails, we got them printed discretely just behind the glazing bars, just like the window company does on all their other jobs (that probably don’t use our warranty company).

house2017.01.28 - 7.jpg
the hallowed kitemark

It’s still below freezing but at least it’s sunny and as warm as it can be for the guys working on the back of the house.

2017.01.24-9.jpg

house201701.24 - 3.jpg

The view straight through the house is still pretty special.

2017.01.24-10.jpg
back to front
2017.01.28-17.jpg
through to back

It’s still been freezing every morning, so here’s a gratuitous picture of the frosty Common.

2017.01.25-1.jpg

Before Christmas we had the pleasure of meeting Nick Archer, an artist in Rye who we’re going to commission to create a work for us on this wall. He’s done amazing large scale works with colour which is his speciality, and lots of his pieces are bought by corporations with large lobbies that can fit them. We’ve fallen in love with a particular piece of his below. We’ve even moved the electrics in this room so you see the painting from the kitchen instead of a black screen of tech. The painting will bring the whole downstairs together.

2017.01.28-14.jpg
future home for a Nick Archer painting …
stranded 168 x 132 cms.jpg
… and Nick’s “Stranded” which is similar

As a testament to the cracking-on vibe that is occurring onsite, the roofers and a window guy are onsite on Saturday. This doesn’t happen very often. Spencer and his team are enjoying a little winter sun and practicing their catching skills. I’m told they’ll even be around on Sunday to load more  tiles up to the roof–no cutting or noise to annoy the neighbours, just generally getting on.

There were 20 guys onsite on Wednesday, a world record for St Anne’s!, and around 15 for the rest of days in the week. Lots of juggling with cars, gear, deliveries and tea.

2017.01.28-1.jpg

house2017.01.28 - 1 (1).jpg
action stations

2017.01.28-2.jpg

2017.01.28-3.jpg
there’s an X on every fifth course to show where extra nails have gone for building control

Inside is looking very different day by day with the addition of each window. We can start to set our minds to decorating this beast, and thinking of things like curtain returns and furniture.

2017.01.28-4.jpg

Some of the windows died en-route to their final destination which is sad considering all the love that goes into each one. But it must go with the territory and there’s only one dead soldier so far.

2017.01.28-5.jpg

The pipework to bathrooms in the first floor has been installed on the ground floor ceilings throughout, and it pops through the floor when needs be.

2017.01.28-6.jpg
pipes, windows, & electrics
2017.01.28-13.jpg
waterworks in the study ceiling

One cool thing in the underfloor heating is the sensor setup. Tracks in the screed were avoided to install a sensor unit that fits between the pipes and connects to a programmable unit on the wall. This unit controls a zone, and there are units dotted around the house. Will be neat to use!

2017.01.28-10.jpg
shower room sensor spot

Another M&E thing we’ve got is a mechanical extract that runs from a central hub to each wet area and the coats closet with all the electrics in it. This unit will raise the circulation in the house so we don’t get condensation and then mould; part of building regs and calcs on the size of the building…. (?)

There was a debate early on about how to cross the vaulted area with the MEV pipes to the shower-room on the west side of the building. At the time we talked about possible fixes such as boxing it in around the apex of the master bedroom ceiling, or adding a second extractor fan for just that bathroom, and all sorts of complicated ideas–none of which were particularly enticing. But in the end James got the guys to run the pipework over the entire ceiling between one roofline and the other. Pretty impressive!

The photo with the silver MEV pipework shows the underside of the roof having been tiled, and the right side still to finish. You can see the lovely blue sky through the Tyvek  and battens on the unfinished side and more blue sky all along the ridgeline.

2017.01.28-7.jpg
silver MEV pipework

The front of the house upstairs is pretty dramatic. James and the guys continue to put up extra Tyvek and insulation whenever they can to protect it. These are the most precious windows ever! And it’s great to know that they think so too.

There is still a teensy bit of floor to left screed still because the team had brought just slightly too little gear with them last weekend. They come up from the south coast to do the work and they have to do it when the site is not overrun with subcontractors. They must have been horrified to find they’d come up short. They’ll come back soon, and it will be good to be finished to cover those delicate pipes.

2017.01.28-11.jpg
landing looking west
2017.01.28-12.jpg
landing looking south through the master bedroom

The lone windows guy installed the side lights to the front door today. At least it’s a little warmer this morning on the north side for him. And the forecast is good going forward, so here’s hoping for a good few weeks with lots of activity!

2017.01.28-15.jpg

Week 41

Lots of decisions in the background. Lots of cold cold weather.

Underfloor heating upstairs, wiring for the alarm system and sorting most of the first fix electrics was the name of the game this week. The window guys had a break and returned to base for a week while we wait for the next shipment of windows.

The guys came to screed the first floor, and they couldn’t get into their shed in the morning because it was frozen shut at -8 C. They rescheduled for Saturday only to find that it was still -6 C and the pipes onsite had frozen leaving them waterless.  They worked around it by running the hot water to make up their mix through the space heater. Nice. But they managed.

house201701.24 - 4.jpg
future toastiness
Not many photos onsite this week. The kids have university interviews, with lots of travel hither and thither, some of the team are on holiday this week making for a lack of meetings, and there is a lot of stuff going on for me at work. Work gets right in the way of site visits. And all that frozen scaffolding makes for a pretty challenging time onsite.

The windows are lovely, but I feel we may have cut too many corners by not having enough openings in the master bedroom and the hallway where the tall windows are. We’ll see.

Now, back to the electrical drawings.

 

Week 40

New Year, new resolve, ….. we WILL be living in this house before this year is out. Having seen the potential of this place in 1999 and bought it and moved in by Feb 2000, we’re finally going to have this noose around our necks lifted. We’ve hemmed and hawed for so long about the most cost effective way to renovate or fix or whatever, and we’ve lived in such an ambiguous state for so many years, that it’s quite incredible to think that it will ever be FINISHED. Don’t get me wrong, I’m sure there’s finished, Finished and FINISHED, but just to have a house that doesn’t leak and looks half way decent will be a huge improvement on previous years. After all, the kids know nothing else!

And of course, it will be way better than half way decent. You can see from the time-lapses that there is a bunch of activity onsite these days: electricians, carpenters, flooring, heating, windows….. It’s starting to really crack on.

The window guys started on 9 Jan, so all the oak subframes had to be installed beforehand.

house20170107 - 1.jpg
family room
house20170108 - 1.jpg
they will eventually fade to grey

James has kept a bit of celotex on the sills to protect them once they’re in.

house20170108 - 2.jpg
shocking weather
house20170112 - 1.jpg
door frames being built and getting installed

Terry and Josh have been quietly getting on with wardrobes upstairs and kitchen framing downstairs.

house20170112 - 2.jpg
kitchen studs

house20170113 - 1 (1).jpg

The window guys arrived en masse in a team of four or five depending on the day. The last time we saw this gear was up North, and it’s weird to see the frames and glass in the house at long last.

house20170112 - 3.jpg
test pane

One of the guys was a specialist pointer: each of the windows has a silicone bead running around the frame between it and the oak and another between the frame and the glass. I’ll get a macro shot of the beading next week, but there is a precise technique and the finished product is gorgeous.

house20170112 - 4.jpg
waiting patiently for installation
house20170112 - 5.jpg
master bedroom
house20170112 - 6.jpg
master pane
house20170112 - 7.jpg
brave man with a hammer

house20170112 - 10.jpg

house20170113 - 1 (2).jpg
master bedroom from inside

There are still loads of things to do around and about. The roof tiles should arrive this month, but since it’s a stand-alone piece outside the Critical Path, it kind of doesn’t matter when they go on. The building will look very different when it’s got its hat on.

house20170112 - 8.jpg
roofline

The first floor is being covered with celotex insulation prior to the underfloor heating next week. Wednesday is screed day, and this works perfectly with the windows guys because they’re awaiting delivery of more gear from Grantham which arrives the following week, so they’ll take a little break from this job while the floor sets. All very time-dependent and complicated.

house20170112 - 9.jpg
bathroom

We had a stairs meeting this week with Tony the Blacksmith and Colin and Gary from the joinery company. The goal was to sign off on the plans and get into production which is 10 – 12 weeks from sign to installation. Tony brought models of his spindles and had a great conversation with the joiners. In a total Goldilocks moment, we’ve decided to use the middle sized section of spindle. Plans were signed, and production lines confirmed, so we’re looking at end of March to see these in real life. Tony says he’s making progress with the lantern as well.

house20170113 - 3.jpg
oodles of spindles

It also snowed this week.

house20170113 - 6.jpg
disgusting weather
StAnnes00009.jpg
frozen camera housing
house20170113 - 9.jpg
snow on scaffold through the new windows
house20170113 - 5.jpg
door handles
house20170113 - 8.jpg
front bay–with windows (most of them…)

https://youtu.be/5GacEAXtvVMhttps://youtu.be/QKmUF9l0b4whttps://youtu.be/t4UgZs9S9-ghttps://youtu.be/-t7Jhgjy5Vg