Week 24

Friday

A visit to the joinery company that is doing the stairs, the oak subframes for the windows and the external doors.

Paul is our Area Manager and he’s always said to come on down and have a visit. As we’re getting to some crunch points with decisions, it sounded a great time to scoot to Andover to have a look. Today I got the chance to meet Gerald the MD, and he and Paul both took me for a tour of the factory before sitting down to talk design.

The factory is enormous. But it’s family run and has grown from a shed to a business with over 60 employees in a generation. There are 28 guys on the factory floor spread out into separate areas. There is a room for the initial cut as the laminated boards arrive from Germany, another for making tenons and mortice joints, another for windows, another for painting, another for stairs, and another for doors with CNCs, lathes, wrapped finished pieces and components all neatly placed in stacks per job. I’ve probably left out a few rooms,….but the guys were really busy as we went around, and everyone was really friendly and very patient with my picture-taking.

I was thrilled to see our job taking up (a large part of) the floor!

2016.09.23 - 1.jpg
window subframes

2016.09.23 - 6.jpg
… and more window subframes with joints
Laminates are used for the uncut beams so there won’t be any knots. They’re cut to section size on the outside dimensions, then they’re sliced on the remaining dimension to length, and finally, the mortice and tenon joints are cut in. Gerald fitted one of our subframes all up and assembled for me to have a look; the joints are seamless and the facing sides beautiful.

2016.09.23 - 3.jpg
our job. all three stacks with little white labels waiting to be cut
There are over 70 windows in the house, and each requires more than four bits of wood to make the subframe. Some of the larger pieces, like the sills, are made of two pieces with an air gap in between them to let them bend and settle on installation (I think?!)

We’re having clear Osmo coated frames and doors to retain the natural look of the wood, but it was still awesome to see the painting room. The windows are suspended on a series of hooks strung up to a yellow motorised track. They trundle past the guys to get a good coat of paint (150 microns a layer) and continue on to the other side of the wall to dry. Water is spritzed in to keep the paint from drying too quickly, so the room feels slightly tropical. This waterbased paint takes about 1.5 hours to dry, but our clear Osmo will go on with a brush and take 3 days to cure entirely.

2016.09.23 - 4.jpg
the painting room

2016.09.23 - 5.jpg
some stairs (not ours yet) and CNC
The stairs will be cut on a giant laser-guided CNC machine. I got to see a partially-build curved staircase made of gorgeous walnut; Paul had wanted to check the progress on it as he’d seen it the week before and it’s great to see these things evolve. Each piece for every job is drawn up, plugged into the computer and CNC’d to fit together perfectly. This particular job was gorgeous, and the whole operation is a real engineering marvel.

I’ve come away with some samples of different sized newell posts, a picture of cross sectional balustrades, two actual balusters to think about, and a lot of information about the front door from a discussion with Paul, Gerald, and Sean the Main Technical Manager. It’s going to be a busy weekend thinking through all this.

From Andover back to base, I had a chance to climb up the scaffold and have a look at the new bedrooms.

2016.09.23-2.jpg
West Wing

2016.09.23-6.jpg
east wing

2016.09.23-5.jpg
door to front bedroom

2016.09.23-3.jpg
back bay, pre-oak
What was the name of the first lady to fly across the Atlantic? What was the name of her airplane? What was the name of the Japanese city that was spared the atomic bomb and why? What were the names of those bombs? We’ve already nailed the name of the plane that dropped them along with the name of the guy who broke the sound barrier. We did moon landings a few weeks ago, and I’ve overheard a discussion about the bass line in Eagles songs when the guys first came onsite. I probably need some help brushing up on general knowledge if I spend too much more time onsite….

2016.09.23-4.jpg
Paul and Dave: pros
https://youtu.be/PfuIcSZRgdA

Thursday

Back to Sussex we go!

2016.09.22 - 1.jpg
Bluebell Railway from the car park
Another breathtakingly gorgeous drive in the time machine to visit our oak structural frame. It gets loaded on Friday and will be onsite on Monday. I will miss this drive! Neil gave me a tour of the pieces, and in particular wanted to show me the showstopper piece he sourced for us.

2016.09.22 - 2.jpg
ta-da!
2016.09.22a-1.jpg

The single-piece curved beam is a success. 2016.09.22 - 3.jpgThe alternative would have been to cut it out of
a very large section like he showed me in the sawdust on the floor. This would have been super expensive and not quite as nice because the grain would have made a horizontal trace to follow the growth of the original plank. The more cost effective alternative would have been to have cut two or three pieces and join them, and this is what we had specified originally. The many-pieced bends are what you see around town with other builds of this design. Ours will be the only single piece beam. Whoop whoop!

2016.09.22a-4.jpg
backs of brick infill bits

2016.09.22 - 4.jpg
more of our job
There are over 60 pieces for the rear bay alone. They’ll be stuck on the back of a lorry over the weekend, then up to us on Monday early a.m. They’re all labelled (red pen for front and green pen for back), and it’s great to visualise where the bits will fit in according to Dave’s drawings.

2016.09.22a-6.jpg
upside-down cross piece for gable with window rebates on the top

2016.09.22a-5.jpg
er, … a truss strut
It’s amazing how casual they are about taking these enormous beams and cutting chunks into them. They tell me that all the hard work, i.e. measuring and planning, has already been done, so this is the easy part. Very impressive!

On the way back, I put the anchors on as I passed the Bluebell Vineyard shop. A quick u-turn later and I was in the car park alongside a very Californian looking setup with tasting room and a nice few rows of well-tended vines. All was well, and then a great big tour bus from Eastbourne carrying a large number of pensioners arrived. I thought I might have just enough time to buy a bottle of their finest before they wandered in, but they were quick, and I was too late. My bottle of bubbles will have to wait until next time. And I think there just might be a next time because we’ve got designs on a nice countertop shelf for the basin in the downstairs WC. Back to Neil’s this autumn I think!

2016.09.22a-9.jpg
from idyllic Sussex….

2016.09.22 - 6.jpg
… to rainy base for our Thursday site meeting
Paul the electrical guy was due to arrive, but he was stuck on the M25 unable to move. Apparently a crane (nothing to do with us!) blew up into a massive fireball on the M40, and travelling anywhere near London was a bit of a no-hoper today. We look forward to meeting Paul another day.

We also welcome Claire aboard the good ship St Anne’s. She’s designed an awesome kitchen, and she was onsite this afternoon to measure up and ensure that the drawings matched reality. Apparently this isn’t always the case, but on this job the plans and the build match decisively. She’ll now make up a set of drawings for review, right down to the lights, sockets and tiling. We’re looking forward to that!

Monday

2016.09.20 - 1.jpg

Continuity–hooray! James is back onsite overseeing everything in his first pair of consecutive weeks in the job. Things are ticking along smoothly; but the brick team is running out of vertical interior walls to keep busy before the oak frame is installed next week.

We had a massive site meeting of the minds today: Dave the Architect, Tim the Contractor, Tom the Steels guy, Neil the oak guy, Paul the joinery guy, and of course James the Site Manager, Ben the Project Manager, and me tagging along trying to learn as much poss. Today’s lesson was: What’s a padstone? For those like me who have not a clue, these are extra strong blocks (not bricks) that the steel lintels sit on. Double doors require a steel above them to support the brickwork above, for instance. The brick team need to know the dimensions of the steels so they can set these padstones in the right places. Should be fine, right? They’re on the drawings. But if the steels are still somewhere between the drawings and physical arrival, the brick team usually waits until they’re onsite to line them up or they risk unbuilding what they’d already built off plan. And as luck would have it, this part of the project coincided with the engineer’s summer holiday plans, so we’ve been delayed in getting them even on paper. We’ve been playing the game of keeping the brick team onsite doing the interior blockwork when they’d really rather be getting on with setting the padstones and building the exterior walls. Next week, hopefully.

2016.09.20 - 3.jpg
crowded house
There was much discussion of how the oak frame will tie into the brick work. The frame is a really special thing–it’s meant to be completely self-supporting. As in, if you put it all together in the garden, it would stand up by itself. I totally respect the integrity of the structure and think it’s really important to have it do what it looks like its doing, and not pretend. A nice part of the build. We’re all looking forward to seeing it go up, so next Monday will be an exciting day.

There is a large A-shaped steel on the rear of the building between the oak frame and the brickwork that has yet to be finalised and manufactured, and this will be mainly to support the roof ridgeline. The roof is a very complicated thing, and although much of today’s meeting was spent discussing erecting the oak frame, Dave was on hand to make sure we don’t mess up the roof dimensions so that the pitch of steels matches the pitch of the oak once it’s up. Exactly. Tim wants to minimise the number of crane-days (too right, they’re bank), so it’s quite a job to line up the trades requiring cranes all on the same day/s. There are steels, oak frame and floor panels to juggle.

2016.09.20 - 2.jpg
front gable
One decision that had to be made today concerned the bowed beam on the front porch. We’ve spent a lot of time trying to get the look of it right: how thick, where to place it front to back in the frame, what circumference the bend should be…. But just to make things interesting, Neil arrived today with an idea. He said that he’s very lucky in that he has the luxury of spending time (he’s been part of the job since February, so that’s a while!) sourcing pieces for his jobs from all over Europe, and that he had found the Perfect Beam for this job. The one he’s picked is bent at just the right angle across the whole of the piece so that the grain follows the bend beautifully, and the beam can therefore be made of one piece. Previous designs had two or three chops in it to achieve the right bend. Dave says the chopped approach would make the build look like a pub. St Anne’s Arms? Clearly the single piece is the better option. It will be slightly skinnier as a result of The Perfect Bend, and it will now match the width of the vertical beams between the windows rather than the chunky vertical corner pieces. I’m sure this will all make sense when it’s up, and I imagine it will look quite elegant.

Ben says it will be amusing to watch me give tours of the finished product. He reckons I’ll be waxing lyrical about the cunning oak-brick tie-ins and the effective placement of the cranked steels when really all they’ll really be interested in is the nice paintwork and some colourful vases. We’ll see if I will be able to contain myself….

In the meantime, Mick, Paul, Dave, Glen and Johnny just keep happily laying more and more bricks…..

 

 

 

Week 23

Lots of progress upstairs and lots of progress behind the scenes this week.

The upstairs blockwork is being laid, and the rooms are coming to life. The front bedroom has a bit that overhangs the study downstairs, so until the oak frame goes up in a week and a bit, we can’t lay the entire floor. Some of the elements look really weird right now: he linen closet alongside looks miniscule, and the bathroom window looks huge. I haven’t had the nerve to go all the way around the building on the scaffolding yet, so I’ll leave it to take more photos next week.

2016.09.17.1 - 2.jpg
front bedroom
2016.09.17.1 - 3.jpg
west side of the house

The pre-oak porch is a funny thing at the moment. The brickwork looks great, but it is very hard to visualise where the oak and front door will be and how this all fits with the stairs in the current framework of steels and blockwork.

2016.09.17.1 - 4.jpg
sick-inducing shot of the porch area

James has been busy clearing the area around the drive. That holly hedge has been there forever, and it was always ropey, difficult to trim and gave the cars scratches on the bumpers as we reversed out of the drive. Glad to see the back of it, but I wonder if my neighbour is just as thrilled now that there is an unbroken view of the site.

2016.09.17.1 - 1 (1).jpg
de-gardening

The staircase we’re considering will be something like the one in a photo that my sister sent. It was of a famous ranch house in California built in 1915. I like the spindles and most parts of the newell post.

IMG_4663.jpeg
ranch house staircase

The front door will look something like one from another house that was built locally. Hopefully we can get our joinery company to match the design.

DSC_1947.jpg
idea door

We’ve spent very little time onsite this week, mainly do to work commitments, but lots of time choosing stuff. We’ve sorted 85% of the bathroom order, we’re expecting a quote for the front door any day, and we’ll be thinking more about the staircase this week. I’ve gone through the electrical and small power plans with a fine tooth comb as well. You think you can get all the info you need from the plans, but it’s amazing how different it is to walk through one of these half-built rooms and think “Where am I going to put the light switch?” If you have to think about it too hard, it’s probably in the wrong place.

This week coming up will be choosing tiles, getting the kitchen and bathroom orders finalised, re-choosing roof tiles to a more cost-effective option (don’t ask–this will be iteration #3), sorting out the fireplace design, and talking to a couple of interior designers to make sure we don’t make stupid mistakes with colour and furniture. The more help I can get on this project, the better!

 

Week 22

First off, here are a bunch of stills of animal life onsite:

stannes00007 stannes00008 stannes00006 stannes00005 stannes00004 stannes00003 stannes00002

This week has been interesting in terms of staff changeover when lots of things are going on all at once. Welcome to Paul who is looking after the site while James is on holiday after taking over from Nic (phew).

The biggest event was the arrival of concrete plank flooring for the first floor on Thursday. Paul had his work cut out in organising minimal parking at the top of road so the crane and lorry loads of planks could make the turn, and kept his team at either end of the lane while the planks were offloaded. We’ve already had one angry neighbour on the phone concerned about access and the possibility of needing an ambulance should the need arise (?). When these things happen, it does make me wonder rather why on god’s green earth, when we’re the residents who have been here the longest of any of the 12 houses down the lane bar one, we’re investing our future in an area that is becoming increasingly less and less tolerant. Does civility have to be the price we pay to live here? I hope not, and I remain firm in trying to rise above the pettiness and try to see the good in people even when they’re struggling and perhaps at their worst. But the the guys did a fantastic job, the road wasn’t blocked, and only the bus from one of the local private schools opted not to travel the extra distance to the end of the road. So all in all, a success!

Dulux was back from the initial demolition, doing his best to fend off potential parkers from the top of lane, and he was chuffed to see how the build was coming on. Hopefully we’ll see him again soon.

But before that, the last minute adjustments to the steels were put in place on Wednesday. The last minute adjustments quickly turned into a last minute replacement of every piece, but it was finished by the end of the day. The bricks team couldn’t be onsite with this much action, so it was a good time for them to take a day doing another job and the scaffold team raised the level of the boards while the steels-crane swung over their heads.

2016.09.07 - 1.jpg
crane positioning a steel over the living room on Wednesday
2016.09.07 - 2.jpg
beauty in scaffolding

The weather went from oppressive and overcast in the morning to weirdly-oppressive and gloriously sunny in the afternoon on Wednesday.

2016.09.07 - 3.jpg
raised scaffold all ready for first floor planks

 

2016.09.09 - 3.jpg
second crane in a week, this one for planks on Thursday
2016.09.09 - 4.jpg
and here’s a plank

The team worked seamlessly with one guy on the truck sorting the lifting chains and two guys on the roof putting the planks in place.

 

Week 21

We’ve come a long way in this build….

cropped-dji00159-1.jpgcropped-st-annes-pre-construction.jpg

The guys had a lot going on after the bank holiday: steels, cranes, personnel changes, rain. They’ve been steadily going upwards and we’ve been cracking on with decisions. We’re mostly there on bathrooms, kitchen, fireplace and roof tiles. We’re getting there on flooring and wall tiles.

The steels arrived on Wednesday. There are over 50 pieces in this build. There is a slight hiccup with the sizing of some pieces in manufacture, and after much checking some of them will need to be re-installed next Wednesday before the upper floor goes in.

The overhang on the west side of the front elevation is coming along nicely, and the steel is placed on the piers to take the load for the upper brickwork.

2016.09.04 - 4.jpg
overhang from the living room
2016.09.04 - 5.jpg
front elevation of the living room

The overhang on the west side of the house near the garage is larger and leaves a gap from windows to piers big enough to walk under. I’d better get on an plan the landscaping out the front in case we want some raised beds before it all gets paved over.

2016.09.04 - 6.jpg
west front elevation
2016.09.04 - 7.jpg
bird’s eye view looking into kitchen
2016.09.04 - 9.jpg
the garage in all its glory
2016.09.04 - 10.jpg
more steels across the entire build
2016.09.04 - 11.jpg
kitchen space

Roof tiles are very difficult to choose. We’ve spent some time looking through brochures and spent about a week developing a good mix of shades to make the whole project seem weathered–like it had been there for decades. When we presented our carefully considered combination to the builders, he said we were nuts. Why spend all that extra on something a) you won’t see, and b) will fade within a year? So we have decided on a single dark tile for the roof and another single reddish tile for the hanging bit on the west flank. Tick.

2016.09.04 - 12.jpg
we’re going for the left hand bunch